APS – 500kV Four Corners- Moenkopi Storm Damage Repair - Contruction only

Replaced/repaired 3 lattice towers and 2 lattice tower foundations damaged by a tornado. Removed 3 collapsed steel towers and replaced with 3 new 130' T2 500kV single circuit transmission line lattice steel towers with new foundations. Move 2 existing lattice steel towers to new foundations in an emergency situation. Work had to be completed under extreme time constraints and in very strenuous weather conditions. Project completed in 23 days allowing 500kV line to be returned to service.